Hmm let's talk about time lines.
The first race is Feb 23 2014, homologation inspection is to take place 30 days prior to the first race or by January 31st.
EBR must certify that it has shipped or has bills of ladings for
125 motorcycles by January 23rd or no later than the 31st.
41 Dealers at present at 6 machines each means they have a back log of 246 machines.
Production began last week, and you figure they are closed the week of Christmas and a few days for New Years, and weekends, they've got 34 days to build the bikes. That means assembling, testing and QC roughtly 3-4 bikes a day. That's alot, for machines that are effectively hand built.